What the scores mean
The score is severity times likelihood. These are the bands this risk assessment matrix uses, and what a crew would normally do at each level. On a 3x3 grid the top band is high; there is no extreme.
| Level | 5x5 score | 3x3 score | What to do |
|---|---|---|---|
| Low | 1 to 4 | 1 to 2 | Keep the normal controls in place and carry on. |
| Medium | 5 to 9 | 3 to 4 | Check the controls are in place before work starts. Look for a way to lower it. |
| High | 10 to 16 | 6 to 9 | Add controls before work starts, and have a supervisor agree the plan. |
| Extreme | 20 to 25 | n/a | Do not start. Change the job or add controls until the score comes down. |
5x5 risk matrix: severity and likelihood scales
On the 5x5 risk matrix, each side runs from 1 to 5. Use the descriptions below as a starting point and agree them with your crew, so two people rating the same hazard land in the same cell. Hover over a row or column label in the tool to see the same description.
| # | Severity | Likelihood |
|---|---|---|
| 1 | Negligible: No injury, or first aid only | Rare: Hard to picture it happening on this job |
| 2 | Minor: Medical treatment, back to work the same day | Unlikely: Could happen, but not expected |
| 3 | Moderate: Injury that keeps someone off work or on light duty | Possible: Could happen on some jobs like this |
| 4 | Major: Serious injury: fracture, amputation, hospital stay | Likely: Will probably happen at some point |
| 5 | Catastrophic: Death, or permanent disability | Almost certain: Expected, or already had near misses |
How the risk assessment matrix works
- Name one hazard. One hazard per rating, written so anyone can picture it. Our job hazard analysis guide shows how to describe one.
- Pick the severity. Think of the worst harm that could reasonably happen, not the luckiest outcome.
- Pick the likelihood. OSHA calls this a judgment call: near misses or past injuries on the same job push it up, and so does a hazard that is exposed and easy to reach. [OSHA]
- Read the score. The cell gives severity times likelihood and its level.
- Add controls and rate it again. Switch to "After controls" and pick the new cell. If the level does not drop, the controls are not doing enough.
Two cells can share a score and still mean different things. Severity 5 with likelihood 1 scores 5, the same as severity 1 with likelihood 5, but one is a rare death and the other is frequent first aid. Read the severity as well as the number, and treat any hazard that could kill or disable someone with care even when the score is low.
What OSHA says about rating hazards
OSHA's Recommended Practices for Safety and Health Programs put the idea behind the matrix in one line:
“Determine the severity and likelihood of incidents that could result for each hazard identified, and use this information to prioritize corrective actions.”
The same guidance says to deal with the hazards that present the greatest risk first. [OSHA] When money or time is short, OSHA's hazard prevention guidance says to fix things in order of risk:
“When resources are limited, implement measures on a "worst-first" basis, according to the hazard ranking priorities (risk) established during hazard identification and assessment.”
OSHA's Job Hazard Analysis booklet uses the same two questions to choose which jobs to analyze first: those with hazards most likely to happen and with the most severe consequences. [OSHA] These are guidance documents. None of them sets a matrix size, labels or score bands.
On US Army Corps of Engineers work, the safety manual EM 385-1-1 does define a risk matrix for its activity hazard analysis, with four severity and five probability categories:
“Severity is categorized as catastrophic, critical, moderate, or negligible. Probability is categorized as frequent, likely, occasional, seldom, or unlikely.”
That matrix gives a risk code of E, H, M or L, and on those contracts it is the one to use, not this one. [US Army Corps of Engineers]
Using the matrix in a JHA or JSA
Rate each hazard in your analysis before and after its controls, then press "Copy the JHA row" and paste the line into the comment column. Our free JHA template and JSA template give you the whole form in Word and PDF to print. A risk matrix template on paper works too: print the blank grid and keep it with the crew's forms.
Pick controls in OSHA's order: change the equipment or the work area first, then the way the work is done, then PPE. [OSHA]
Risk matrix template to print
Press "Print the matrix" with no cells picked and you get a blank risk matrix template: the grid with its scores and colors, the severity and likelihood descriptions, the score bands and lines for the job, the date and who assessed it. Pick cells first and the printout marks them B and A, with your hazard and controls written out, ready to staple to the JHA. Choose "Save as PDF" in the print window to keep a file copy.